A 550-ton crawler crane
used as a main lifting crane

Tower foundation is ready

The tower delivered to
the site

Ready, go

Co-working of a main lifting
crane and trailer crane. The trailer crane is to prevent the tower from sliding
during lifting.

The tower is being lifted
up

Positioning the tower into
the foundation bolt

The tower is installed